Palace of the Patriarchate
Field of Expertise
Construction Design
Technical Consultancy
In order to meet the requirements of architecture and structural strength, the design team of the consolidation works had to identify non-invasive means of intervention, which are hidden in the existing structure of the building, without affecting the interior and exterior style of the architectural monument.
The proposed consolidation solution can be divided into three main branches, namely: the interventions made to the exterior of the building, the new reinforced concrete elements that merge with the existing structure, and the tie rods embedded in the walls of the building.
An increased importance is represented by the overall behavior of the building in relation to the land on which it is located. Over the years, due to the terraced profile of the land, the building (especially its southern end) has undergone a tendency to move to the South, namely to the foot of the Metropolitan Hill, it being practically a retaining wall. This tendency determined the obvious sectioning of the building, by the appearance of cracks between the northern body (from the top of the hill), 2 levels high, and the southern one (from the base of the hill), 4 levels high. At the same time, pronounced cracks appeared between the south wing and the rest of the Palace.
To stop the trend of moving the Palace to the South, the design team decided to introduce a pilot front and a support belt designed to resist landslides. This “retaining wall” consists of 0.88m diameter piles that descend to a depth of 12m. At the top, the pilots are supported by a massive beam 1 meter high that laterally supports the southern body of the building. At the same time, the massive beam also represents the foundation of two external consolidation walls. The arrangement of the pilots was provided alternately, in two rows, to increase the capacity of the support system.
The retaining wall is located outside the existing building, which is only adjacent to the structure of the building. The wall surrounds and encloses the southern head on 3 sides, practically blocking its movements both in the North-South and in the East-West direction.
The main method by which the capacity to take over the seismic loads has been increased is represented by the erection of 5 rigid reinforced concrete cores arranged around the meeting room, and by the introduction of new external walls, which are built in the southern body of the Palace. to stiffen. The reinforced concrete walls and cores are born from the foundations of the building, in the basement 2 or 3, and go up to the plate above the second floor, ie the attic plate. Their foundation is made on piloted erasers, individual for each core. The diameter of the mini-pilots is 0.4m, they also have the plug at 12m below ground level.
The location of the newly built cores was chosen so that they do not affect the significant architectural details of the building. As a result, the nuclei were placed in less accessible spaces such as technical spaces, sanitary functions, or vertical circulation. The walls of the cores have a thickness of 60 cm in the basement, of which 50 are embedded in the old masonry walls, and 10 cm protrude from the front of the original walls. On the upper floors, the thickness of the walls decreases, reaching in some cases 40 or 30 cm.
A different approach was needed to shape the walls bordering the corridor around the central hall, part of the P1 core. Like the core, the walls are born from the basement and end in the plate above the 2nd floor. However, they could not be perfectly aligned vertically, being necessary to mask them at higher levels. Basically, the 60cm thick walls are located in basement 2 in front of the old walls, then in basement 1 the newly built wall is embedded in half (30cm) in the old masonry, so that later, on the ground floor and above it, the walls are completely embedded ( 60cm) in masonry. The passage between the walls is made by high capacity transfer beams, section 90x120cm.
Address
25 Dealul Mitropoliei Alley, Bucharest
The positioning and sizing of the walls of the nuclei was done so as to balance the rigidity of the building, noting that the nuclei are arranged especially in the areas adjacent to the classroom. The area of the eastern body, more regular and richer in walls, did not require a considerable addition of rigidity. At the same time, the east wing was protected from works especially by the opinion of the experts of the Ministry of Culture, which limited the possibility of intervention on it, in order to protect the architectural decorative elements of high significance.
Individually, however, the reinforced concrete cores are not enough to improve the seismic behavior of the building. Given the plan size of the Palace and the relatively large distance of the new nuclei between them, it is necessary to connect them and show their solidarity with the whole building. Through this, the efforts generated in case of an earthquake in the entire building will be redistributed to the new reinforced concrete cores, the building being forced to work as a unitary whole.
Basically, it was necessary to make horizontal rigid washers over the ground floor, 1st floor and 2nd floor, which, according to the proposal of the consolidation project, were to take the form of thick reinforced concrete slabs.
In the case of the tiles above the ground floor and the 2nd floor (Figure 19.a and Figure 19.c), they will be limited to the circular area around the hall. Across the ground floor, the new board has symmetrical extensions in the East-West direction, extensions that are no longer found in the case of the board above the second floor. For the rigid washer above the first floor (Figure 19.b), it was initially proposed to adopt the solution of a general plate, which would have spread over the entire level. The reinforced concrete slabs are meant to redistribute the efforts generated by the side loads, to the new raised reinforced concrete cores.
Another applied consolidation solution is the introduction of tie rods in the existing masonry structure. They will be arranged in both horizontal and vertical directions. By introducing them, the ductility of the masonry walls will be improved, which is normally characterized by fragile failures, unfavorable in case of an earthquake. The tie rods are made of 32mm diameter PC52 steel bars, which cross the building, being inserted in holes drilled through the walls of the building. At the same time, the steel bars have the role of connecting the sections of the building together, stopping their tendency to move and move away from each other.
In addition to the main consolidation solutions established by the design team, it was decided to sew some masonry regions strongly affected by the differentiated settlements. Sewing will be implemented especially in the areas adjacent to the southern body of the building, areas strongly affected by differentiated settlements and the tendency of that area to slide to the base of the hill. The solution of sewing the masonry will be made only after the execution of the external support wall, meant to stop the additional translation of the body to the South. At the same time, additional sewing will be performed in the area that delimits the northern section (2 levels high) from the rest of the building, built on the slope of the land, and therefore higher.
Description
The consolidation of the Palace is a project of increased difficulty, given the size of the building, the abundance of architectural details and its location on a sloping terrain, unsuitable for such a building. The increase of the seismic capacity was achieved by introducing a system of rigid reinforced concrete cores, connected by means of horizontal rigid washers, and the counteracting of the effects of the difficult ground was done by introducing an "external retaining wall" made of piles connected by a beam. massive. The third solution implemented involved the installation of horizontal and vertical tie rods through the walls of the building, these being introduced in the longest drillings ever made through the walls in Romania.
Features
Gross Area:
Number of Storeys:
Special Technologies:
16 250sqm
2B+GF+1F+M
Installation of horizontal and vertical tie rods in the walls of the building, in both directions, in the longest masonry drillings made in Romania at the time of execution
Challenges
The building size, the fact that it had plenty of architectural details and it is situated on a sloping ground, unsuitable for such a building
Description
The consolidation of the Palace is a project of increased difficulty, given the size of the building, the abundance of architectural details and its location on a sloping terrain, unsuitable for such a building. The increase of the seismic capacity was achieved by introducing a system of rigid reinforced concrete cores, connected by means of horizontal rigid washers, and the counteracting of the effects of the difficult ground was done by introducing an "external retaining wall" made of piles connected by a beam. massive. The third solution implemented involved the installation of horizontal and vertical tie rods through the walls of the building, these being introduced in the longest drillings ever made through the walls in Romania.
Features
Gross Area:
16 250sqm
Number of Storeys:
2B+GF+1F+M
Special Technologies:
Installation of horizontal and vertical tie rods in the walls of the building, in both directions, in the longest masonry drillings made in Romania at the time of execution
Challenges
The building size, the fact that it had plenty of architectural details and it is situated on a sloping ground, unsuitable for such a building